Use transaction code MD05 to display MRP list

Use transaction code MD05 to display MRP list

After running MRP, we can use transaction code MD05 to display the result. Below is the screenshot of MD05. We input or select the material number, the MRP area and the plant, then we press Enter button on the keyboard of computer. Below is the […]

The solution of the Project-based Manufacturing which outputs finished products

The solution of the Project-based Manufacturing which outputs finished products

There are many kinds of manufacture enterprises in the world. Some of the companies provide the assemblies to customers. For example, a company undertakes a project to build a laboratory for customer. The company delivers the assemblies (such as experiment instruments, buildingĀ materials, and so on […]

The solution of “Make To Order” business

The solution of “Make To Order” business

This article introduce the solution of “Make To Order” in SAP system, involving the foreground operation and background customization. You can follow the steps below to complete the solution. To see the detailed information, you can click the link of every step to open the […]

The way to display the cost of sales order with assigned orders

The way to display the cost of sales order with assigned orders

In the business solution of “make to order”, we often assign production order to sales order. This article tells you how to display the cost of sales order with assigned orders. STEP 1 Get into business transaction KKAC. Access business transaction via SAP menu path […]

Settlement of production order

Settlement of production order

This post introduces how to settle the cost of production order to material or sales order. STEP 1 Get into business transaction CO03. Follow the SAP menu path “Logistics -> Production -> Shop Floor Control -> Order -> CO03 – Display ” to display the […]

Display the actual cost of production order by using transaction code CO03

Display the actual cost of production order by using transaction code CO03

This article guides you to display the actual cost of production order, we can use transaction CO03 to do this. STEP 1 Get into transaction code CO03. Access via SAP menu “Logistics -> Production -> Shop Floor Control -> Order -> CO03 – Display “ […]

Goods receipt for production order into warehouse

Goods receipt for production order into warehouse

After the production, we need to receipt the finished product into warehouse. This article shares the system operation of goods receipt for production order into warehouse. STEP 1 Get into transaction MB31. Follow the SAP menu path “Logistics -> Materials Management -> Inventory Management -> […]

Goods issue to production order

Goods issue to production order

Usually we delivery raw material to production order before the produce, and this article tells you how to do goods issue to production order. STEP 1 Get into transaction MB1A. Follow the SAP menu “Logistics -> Materials Management -> Inventory Management -> Goods Movement -> […]

Use transaction MD04 to convert planned order into production order

Use transaction MD04 to convert planned order into production order

This article introduces the way to convert planned order into production order by using transaction MD04. Besides, you can use transaction CO40 to convert planned order into production order, if you want to know more about CO40, please open our post http://www.nicesap.com/pp-module/use-transaction-code-co40-to-convert-planned-order-to-production-order.html STEP 1 Get […]

Run MRP by using transaction MD02

Run MRP by using transaction MD02

You can learn using transaction MD02 to run MRP in this post. STEP 1 Get into transaction MD02. Follow the menu path “Logistics -> Production -> MRP -> Planning -> MD02-Single-Item, Multi-Level ” to get into transaction MD02, which you can see below. STEP 2 […]

The way to solve the error “Requirements planning is not active in plant XXXX”

The way to solve the error “Requirements planning is not active in plant XXXX”

The SAP system may pop up an error message “Requirements planning is not active in plant XXXX” when we use transaction code MD02 to run MRP. This is because the requirements planning for the plant is inactive, and this article guides you to solve it. […]

Define strategy group for product planning

Define strategy group for product planning

STEP 1 Find the menu path to configure strategy group. Follow the menu path “SAP Customizing Implementation Guide->Production->Production Planning->Demand Management->Planned Independent Requirements->Planning Strategy->Define Strategy Group” . Plus: Read our article http://www.nicesap.com/ps/how-the-reach-sap-reference-img-interface.html to know more about SAP IMG. STEP 2 Select a suitable strategy group and […]